On March 11, 2022 with the roof of our future main office and Wailuku branch at Kehalani Village Center done, we celebrated the topping off of the building by thanking the contractors and construction workers who have made the work on the building possible thus far. A small group of workers, Board members, Supervisory Committee Members and employees commemorated the occasion in what is currently an open-air branch lobby and toured the building.
Over the past 14 months the ground has been graded, foundation poured, steel and framing for the exterior walls and roof has gone up, and sprinklers installed Currently steel framing for the interior walls is going up, electrical is going in and air condition is being installed. The building is on track for substantial completion by early August, and we hope to be able to move from our Wili Pa Loop location across the street from the Wailuku Post Office and begin serving you at this location in October 2022.